A reorder point is lead-time demand plus safety stock. Set it per warehouse, review it on a schedule, and let the system raise the request.
What a reorder point is for
A reorder point answers one question: at what stock level should we start replenishing this item so it arrives before we run out? Set it too low and you run out while waiting for the supplier. Set it too high and cash sits on shelves as stock nobody needs yet.
Most businesses either have no reorder points at all and rely on a buyer's memory, or set them once during implementation and never touch them again. Both approaches fail when demand changes, which it always does.
The basic calculation
The classic formula is simple enough to explain to anyone:
- Lead-time demand: average daily usage multiplied by the supplier's lead time in days.
- Safety stock: extra stock to cover variation in demand and in lead time.
- Reorder point: lead-time demand plus safety stock.
For example, if Kestrel Workspace sells about six office chairs a day and the supplier takes ten days to deliver, lead-time demand is sixty. If demand and delivery vary, a safety stock of, say, twenty gives a reorder point of eighty. When projected stock falls to eighty, it is time to order.
Safety stock is where judgment comes in. Items with steady demand and reliable suppliers need little. Items with spiky demand, long or unreliable lead times, or a high cost of running out need more.
Set it per warehouse, not per item
An item sold from three warehouses has three different demand patterns. A single company-wide reorder level will be wrong for all of them. In Sundial, each item can carry a reorder level and a reorder quantity for each warehouse, along with the type of request to raise: a purchase, a transfer from another warehouse, or a manufacture.
That last choice matters. A regional depot might replenish by transfer from the main warehouse, while the main warehouse replenishes by purchase or production. Modeling this correctly avoids buying stock for a depot that could have been supplied internally.
Use projected stock, not stock on hand
If you compare the reorder point with stock on hand alone, you will reorder too often. An item with fifty on the shelf might already have a hundred arriving next week on an open purchase order, or might have sixty promised to customers.
Compare against projected quantity instead: stock on hand, plus open purchase orders and planned production, minus open sales orders and material reserved for production. Sundial calculates this per warehouse, and automatic reordering uses it to decide whether a new request is needed.
Let the system raise the request
When automatic reordering is switched on, the system checks items against their reorder levels on a schedule and creates material requests for anything below its level. Buyers then work from a list of requests rather than scanning stock reports.
The requests are drafts for a person to act on, not orders sent to suppliers. A buyer can combine requests, choose suppliers, send RFQs where prices need checking and convert the result into purchase orders. That keeps judgment where it belongs while removing the daily scan for shortages.
Keep reorder points moving with demand
Demand shifts with seasons, promotions, new customers and lost ones. Reorder points have to move with it. A practical routine:
- Quarterly: recalculate reorder levels for your most important items from recent usage and actual supplier lead times.
- Before known peaks: raise levels ahead of seasonal demand, then lower them when the season ends. Put the end date in the calendar.
- When a supplier changes: update the lead time, and therefore the reorder point, on the day the change is agreed.
- For new items: start conservatively and review after the first month of real sales.
Pay attention to items that hit zero despite having a reorder point, and items that never come near their reorder point. Both are signs the level is wrong.
When reorder points are the wrong tool
Reorder points work for items with fairly regular, independent demand. They are the wrong tool for components whose demand depends on what you plan to make. For those, production planning should drive purchasing from the bill of materials and the production schedule, which Sundial's Manufacturing module handles.
We are building Sundial so an AI agent can propose updated reorder levels from recent usage and lead times, explain each suggestion and wait for approval before changing anything. To see reorder levels and automatic material requests on sample data, try the demo.